HULU SELANGOR, Nov 24 — A digital technology pilot project undertaken by the Hulu Selangor Municipal Council (MPHS) has successfully addressed a landslide problem at Pangsapuri Kenanga in Bukit Beruntung.
The slope repair project, carried out in collaboration with IKRAM Engineering Services Sdn Bhd, prioritised residents' safety and well-being while introducing a new approach to infrastructure project management through the integration of digital technology.
The project was initiated following a landslide at the apartment complex on April 22, 2025, which involved a slope failure measuring approximately 14 metres high and 40 metres wide.
In a social media post, MPHS said the project incorporated three key technologies — Building Information Modelling (BIM), Geographic Information System (GIS) and Digital Twin — to improve the efficiency of infrastructure development and management.
The project also successfully achieved nine key outcomes, including completion ahead of the contractual deadline, cost savings, zero major defects and zero lost-time injuries.
It also produced a Level of Development (LOD) 500 Digital Twin model, which was handed over to MPHS as an information database to support future infrastructure monitoring, asset management and maintenance.
MPHS president Julaihah Jamaludin said the project's completion was more than an engineering achievement, describing it as an important step towards restoring an area previously affected by a landslide.
She also emphasised the importance of continuous monitoring and maintenance of slopes and drainage systems to ensure the safety of residential areas.
According to MPHS, the initiative aligns with the Selangor Digital Future Action Plan (DxF) 2026–2030, which aims to realise the state's vision of becoming a Smart State by 2030.