SHAH ALAM, Nov 24 — Various flood mitigation projects involving repairs, upgrades and new infrastructure are being carried out across nine Batu Tiga localities to prevent floods, said Batu Tiga assemblyman Danial Al-Rashid Haron Aminar Rashid.
He noted that the initiatives include the construction of new drainage systems, installation of water pumps, river widening, and the development of mitigation structures in flood-prone areas.
“We have shifted from a reactive approach to flooding towards addressing its root causes through the building of more sustainable infrastructure,” he told Media Selangor yesterday.
Among the major projects is the construction of a floodwall and the installation of two screw pumps with a combined capacity exceeding 2m3/s in Taman Intan, an RM8 million project whose progress was at 97 per cent in October.
In Kampung Kebun Bunga, the installation of 750m of concrete sheet piling and 290m of capping beams has been completed, with the project including the construction of gabion structures, earth bunds, an outlet structure, a retention pond and water pumps.
Meanwhile, Danial said improvements in Kampung Air Kuning involve the construction of a new drainage system and upgrades to pumping capacities to reduce the risk of the river overflowing into residential areas.
In Taman Ros, Bukit Kuda, the installation of a flapgate and the construction of a 1.5m-wide drainage system were completed in May.
The water pump system in Section 23 was also upgraded with a new pump in April, while river-widening works under the Selangor Maritime Gateway (SMG) project and drainage improvements in Section 17 have been completed.
Drainage repair and improvement works have also been completed in Section 18.
In Padang Jawa, two water pumps were installed at a retention pond at a cost of approximately RM600,000, alongside drain cleaning and improvements near SK Padang Jawa.
However, Danial said, the construction of a flapgate at the Jalan Mat Raji monsoon drain is still underway.