Rain, illegal dumping hamper Sg Subang flood project

27 Nov 2024, 4:30 AM
Rain, illegal dumping hamper Sg Subang flood project

By Yasmin Ramlan

SHAH ALAM, Nov 27 — Challenges like constant rain and high river levels are hampering the progress of the Sungai Subang flood mitigation project.

However, state executive councillor for infrastructure and agriculture Izham Hashim is confident it will be completed by next August.

“The project is facing significant challenges, including frequent heavy rain and high water levels during the monsoon transition period, which have hampered construction works such as the excavation and widening of the river.

“Illegal dumping has caused the excavation area to be covered with waste, which has to be removed and transported to an appropriate disposal site.

“Therefore, additional time and costs are required from contractors to complete this project,” he said at the Selangor State Legislative Assembly sitting here today.

Izham said the Sungai Subang flood mitigation project, which began February 5, is slated for completion by August 4.

As of October, completion stood at 18 per cent.

What do you think?

Latest
MidRec
Media Selangor
About Us

Media Selangor Sdn Bhd (MSSB), a subsidiary of Menteri Besar Selangor Incorporated (MBI), is the official media agency of the Selangor State Government. In addition to the Media Selangor news portal (formerly known as Selangorkini & Selangor Journal), Media Selangor also publishes newspapers in Mandarin, Tamil, and English.