SUNGAI BULOH, Nov 19 — The Bailey bridge over Sungai Subang along Jalan Kubu Gajah, installed following a riverbank collapse caused by flooding on November 4, will open to traffic from 6am tomorrow.
State executive councillor for infrastructure and agriculture Dato' Izham Hashim said the bridge was completed four days ahead of schedule, with the opening date originally set for Tuesday (November 24).
“We have also built the bridge at a higher level, approximately one metre above the previous bridge. In addition, we have cleared the area beneath the bridge, particularly the sections affected by erosion and collapse, to provide a wider passage for water flow,” he told the media after inspecting the final construction works on the bridge today.
Izham added that the bridge's installation began on Wednesday (November 11) after preliminary works, including utility relocation, site clearance, and preparation of the bridge support areas, were completed.
“A total of 32 personnel and workers were on duty around the clock. I congratulate them for their tireless efforts, working day and night to complete the bridge in five days,” he said.
The Bailey bridge, measuring 36.6m long and 7.35m wide, has a single span and can support a maximum load of 30 tonnes.
Meanwhile, preliminary work on a new bridge at the site has begun, with physical construction scheduled to start next year.
Izham said that RM20 million has been allocated for the new bridge, which is expected to take approximately 18 months to complete.