SHAH ALAM, Feb 25 — Work to upgrade the drainage system behind Winnie Plaza, Jalan Sungai Chua, in Kajang is expected to be fully completed by the end of March.

Balakong state assemblyman Wong Siew Ki said the progress of the project to solve the flash flood incident is now at 90 per cent since it started about two years ago.

"This area is one of the hotspots of floods if it rains heavily, so it is hoped that the repair will allow the water to flow more smoothly to Sungai Langat," she said when contacted.

According to her, the state government has allocated more than RM1 million for the project which is run by the Selangor Irrigation and Drainage Department with some of the funds used for utility cable alignment.

“Many think this project is not running, actually it takes time because it involves huge costs. We are thankful to all parties who made it happen,” said Wong.

What do you think?

Latest
MidRec
Media Selangor
About Us

Media Selangor Sdn Bhd (MSSB), a subsidiary of Menteri Besar Selangor Incorporated (MBI), is the official media agency of the Selangor State Government. In addition to the Media Selangor news portal (formerly known as Selangorkini & Selangor Journal), Media Selangor also publishes newspapers in Mandarin, Tamil, and English.